Corporation to resume UGD work to link Ondipudur STP

Print PDF

The Hindu     06.07.2017    

Corporation to resume UGD work to link Ondipudur STP


The underground drainage project appears to reach finality with the civic body planning to take up work on Trichy Road in the city.S. SIVA SARAVANANS_ SIVA SARAVANAN  

The civic body will lay the underground main sewer lines for over 20 km

After many false starts, the civic body seems to be ready to complete the last leg of the underground drainage (UGD) project.

The last leg work involves laying underground sewer lines along and across Trichy Road to convey sewage from 17 wards to the sewage treatment plant in Ondipudur.

NHAI permission

The Corporation could not complete the work in the normal course because it had failed to obtain the permission from the National Highways Authority of India for laying the sewer lines on Trichy Road.

After a delay of over a year, the Corporation made an attempt sometime in 2016 but could not secure the permission.

Now, again, after six months, the Corporation was all set to resume work as it had obtained NHAI permission, said sources. The Corporation would lay the underground main sewer lines for over 20 km and ‘lateral’ sewer lines for around six km. It would cut across Trichy Road at 12 places, including near Rajaji Nagar, Kothari Layout, Vivekananda Layout and Pattanam Road. For carrying out the project, the Corporation had also paid Rs. 5 crore to NHAI.

Once completed, the Corporation would be able to convey sewage from areas north and south of Trichy Road to the Ondipudur sewage treatment plant and this would mark the completion of the project the Corporation had taken up in 2010-11 under the Jawaharlal Nehru National Urban Renewal Mission, the sources added.