The Times of India 25.07.2012
Nagpur Municipal Corporation plans to pay architect for own inefficiency
NAGPUR: The Nagpur Municipal Corporation
is preparing to gift lakhs of rupees to architect of its new
administrative building citing cost escalations caused due to its own
mismanagement and delay in getting the building ready. The project cost
of the building was Rs 17.99 crore when it was approved in January 2003.
It has increased to Rs 56.34 crore due to cost escalation and also
increase in scope of works.
Now NMC is considering a proposal to
increase the service charges of the architect from Rs 53.98 lakh
committed in 2003 to Rs 1.69 crore citing increased cost of the
building. The proposal will come up for discussion in the meeting of
standing committee slated for July 27. The NMC had proposed the new
building behind the existing one in 2002. The then standing committee
approved the cost of Rs 17.99 crore on January 10, 2003.
At that time, the committee appointed architect Virendra Khare
at the service charge of 3% of total cost. On February 28, 2005, the
committee approved increased cost of Rs 38.81 crore. The service charges
of architect were also increased proportionately. The committee again
approved a further increase in cost to Rs 56.34 crore on February 24,
2009. Now, the administration has proposed to increase the service
charge of the architect to 3% of total increased cost.
Sources
in the NMC told TOI that cost of the building increased due to increase
in cost of material and increase in scope of works. “The cost would not
have not gone up if the NMC had constructed the building in time as
civic body itself sanctions all works. If the scope of work increased,
that also also was the fault of officials concerned and architect who
either did not define the requirement or couldn’t provide correct
solution. Now, it wants to saddle the tax payers and reward the
architect for this joint inefficiency. Service charges should be
increased only on the amount cost increase because of increased scope of
works and not for escalation,” said sources.
Two other pending
proposals will come up for discussion in the meeting including purchase
of firewood for crematoria. Besides, nine new proposals will be
discussed in the meeting including installation of new traffic signals
at 20 junctions and starting pay and park on three more roads- Variety
square to Baidyanath square road, Baidyanath shop to Bharat Watch shop
road, and Rahate Colony square to Lokmat square.
Besides,
proposal to give work orders to various security agencies for deploying
43 armed security guards, 531 unarmed security guards, and 51 other
guards. Another important proposal is to purchase various items related
to malaria and filaria eradication at the cost of Rs 39.42 lakh.