The Hindu 27.07.2013
Stormwater works to resume
Drain projects in Cooum and Buckingham watersheds were earlier shelved
Stormwater drains work in the Cooum and central Buckingham
watersheds, which were earlier shelved, will soon resume in full swing.
In
a bid to complete all stormwater drains under JNNURM by March 31 next
year, the Chennai Corporation has revoked its earlier order terminating
the contract for construction of the drains. The Corporation council on
Friday passed a resolution in this regard.
Of the 98 works in the
Cooum watershed, 52 works that were terminated citing slow progress made
by the contractor are likely to resume shortly. The original deadline
for completion of the facilities was October 28, 2010.
Work on key
stretches such as Nelson Manickam Road, Anna Salai, Poonamallee High
Road, Arunachalam Street, Anna Nagar Second Avenue, Gandhi Irwin Road,
Egmore High Road, Mayor Ramanathan Salai, Casa Major Road, Raja
Annamalai Salai, Kodambakkam High Road Swami Sivananda Salai, Sterling
Road and Ayya Mudali Street that drain stormwater into Cooum River will
now meet the extended deadline.
The civic body has also decided to
borrow a loan of Rs. 203.72 crore through TUFIDCO (Tamil Nadu Urban
Finance & Infrastructure Development Corporation Limited). The civic
body will incur an expenditure of Rs. 407.44 crore for the project,
being implemented at an estimated cost of Rs. 1447.91 crore.
Civic body revokes its order terminating the contract for construction of the drains.