The Indian Express 18.03.2013
Bhoomi pujan held for food street in Sector 48
After several delays, bhoomi pujan of the first food street in Sector
48 was finally performed on Sunday, paving the way for the construction
to begin at the site.
This one-of-its kind food street will cost approximately Rs 25
lakh. The open food court area will be 50 feet x 50 feet, will have Kota
marble platform and six 7.25 feet x 7.25 feet booths. The food court
will have an open sitting area and drinking water facility. The project
may take five-six months to complete.
The food street will have six kiosks. Once operational, it will
cater to the residents of the southern sectors where a large number of
housing societies are present. A substantial population resides in the
southern sectors.
Area councillor Davesh Moudgil, who along with residents of the
area participated in the bhoomi pujan, said this project had been
neglected for many years and it was an essential requirement of the
residential societies of the southern sectors. There are no restaurants
in these sectors and residents have to travel long distances to eat out.
Recently, the tender for the food street, the foundation stone for which was laid in 2009, was re-allotted.
The food street had hit several roadblocks since the foundation
was laid in December 2009. The tender had been allotted earlier.
However, before the construction could be started, it came to light that
the site that was allotted for the food street was in the way of a slow
carriageway that was to be constructed in the area.
For shifting of the site a little further, revised plans were
prepared. The approval of these plans took several months. In the
meantime, the contractor who had been allotted the contract refused to
start construction, stating that the cost of material had gone up and
the agency would not be able to undertake construction. Thereafter,
tenders were invited several times, but no one was willing to take up
work.
The shortage of construction material was proving to be a
deterrent for the contractors. After three years of laying of the
foundation stone, construction may now start at the site.