The New Indian Express 31.01.2014
Degremont Feels Let Down by KWA

With less than 75 days left, the Kerala Water Authority (KWA)
authorities are confident that the multi-crore JICA-aided drinking water
project can be commissioned on the coming ‘Vishu’ day, as decided. But,
it appears that all is not well between the KWA and the French-based
Degremont Limited, which has been entrusted with the construction of the
intake well and the 174 MLD (million litre per day) water treatment
plant (WTP) and its operation.
Degremont says that the KWA
authorities are least concerned about settling the company’s claim for
cost escalation, which has occurred not due to its fault. Though the
estimate for the WTP and intake well was fixed at `110 crore, the
company claims that it has already spent close to `150 crore and would
require at least `20 crore for completing the remaining work.
Says
Arvind Kumar Sharma, manager-projects and construction with Degremont
Limited, “The work was awarded way back in 2006 and the completion
period was 21 months. Now, almost eight years have passed and the work
is yet to be completed. The labour rates, fuel and material costs went
up like anything over this period. Then, the labour rate was below `200.
Now, it has almost touched the `500 mark. The price of one packet of
cement, which was around `160 then, has now doubled. The situation is no
different as far as fuel prices, material costs and office expenses are
concerned. You can simply imagine the financial burden the project has
caused to us.’’
The procurement of sand, to be used as filter media in
the WTP, from Gujarat is cited by the company as the latest incident of
cost escalation. “When the project commenced, we were told that sand
would be made available from the state itself. But, now, sand is not
available not only in Kerala but also in Karnataka, Tamil Nadu and
Pondicherry. So, we have to source 250 tonnes of sand from Gujarat,
around 2,400 km away, pumping additional money of around `4 crore,’’
says Sharma.
Having executed various similar drinking water projects
across the country and abroad, Degremont officials maintain that the
company has been pumping money despite limited funds as the work in
Kozhikode is very specific due to the uniqueness of the method being
adopted for the construction of the ‘floating’ intake well in the
Peruvannamoozhi dam near Kuttiadi. Now, he adds, “Everybody thinks that
the work is about to finish and pay scant regard to our genuine demands.
We could have stopped the work till our demands were met. But, we are
fully committed to completing the work. We hope the authorities will
understand the constraints and provide the necessary financial support.
We are not seeking a margin, but the expenses which we have incurred
for the project should be met.’’
JICA Project Director K G Harshan
says, “We appreciate the dedication shown by Degremont in implementing
the work despite difficulties and their demands are reasonable to a
certain extent. However, the final decision to sanction claims for cost
escalation should come from the government level.’’
The project
lagged due to the delay in land acquisition and finding an appropriate
location for the construction of the intake well for the WTP. The
authorities were able to identify the location for the intake well only
in 2012, three years after it was supposed to be completed.