Drainage work to be speeded up
Syed Muthahar Saqaf
PUDUKOTTAI: The Tamil Nadu Water Supply and Drainage (TWAD) Board has
chalked out a comprehensive plan for the expeditious execution of the
underground drainage project by March 2011.
The plan divides the town into two major zones for easy execution.
The sewage of both the zones through 14,520 house service connections
(HSCs) and 5,407 manholes will be pumped through a cumulative length of
147.92 km. before being collected at the pumping station.
The collected sewage will be treated at the plant coming up at
Maruppini Grass Farm and the effluent will be released into the Gundar
river.