Urban News

  • Increase font size
  • Default font size
  • Decrease font size
Road Development

Civic bodies slip on June 30 road repair deadline

Print PDF

The Times of India      01.07.2011

Civic bodies slip on June 30 road repair deadline

LUCKNOW: The deadline for road repair set by the state human rights commission (SHRC) expired on Thursday. In fact, the Wednesday's rains had already exposed the tall claims of civic agencies – there was severe waterlogging in several areas of the city owing to dug-up roads and piles of mud made commuting next to impossible.

According to an estimate, work on over 150 km of roads within city is yet to start, leave alone the final concrete-laying. The civic authorities are now contemplating seeking more time from the commission to finish the repair work. Municipal officials said that rains have proved to be a deterrent. "There is a shortage of labourers because of heavy rains. Not much work could be done because of the weather," said additional municipal commissioner P K Srivastava.
"We would be requesting the commission to give us some more time. At least a week's time or so. We will be able to improve the situation as soon as rains cease," Srivastava added.

Meanwhile, residents of several areas had to wade through knee-deep water as heavy rains lashed the city from Wednesday evening onwards. Traffic too moved at a snail's pace on partially repaired roads. Worst-affected areas were the ones where authorities are yet to get the sewer chambers constructed or those where drains are yet to be cleaned. Such areas include Mahanagar and Aliganj. The situation was equally grim in colonies like Indiranagar and parts of Gomtinagar, where UP Jal Nigam had carried out a road-digging exercise to lay sewer lines. The mud made roads slippery and it was impossible to move out. "We were unable to move out as the road is not fit even for walking. It was not possible to drive on the slippery roads," said Kamlesh Bala, a senior citizen and a resident of Shivajipuram in sector-14, Indiranagar. "We have been deprived of our right to have proper roads," he said.

Municipal sources admitted that localities where chambers for the already laid underground sewer lines are yet to be constructed have tough times in store. It is not until the sewer lines are interconnected through these chambers that the sewer system would actually work. This would require that roads be dug-up again. And that's probably the reason for the delay in getting the roads repaired permanently. Engineers associated with the project said that the UP Jal Nigam is expected to construct these chambers before concrete-laying for the roads.

In the meantime, after Thursday's rains, some more areas were in for trouble. "The situation has gone from bad to worse because of the rains," said Sanjeev Bhattacharya, a resident of Ravindrapalli. The roads in a section of this locality were dug-up last year to lay sewer lines. The section is waiting for repairing of roads ever since, residents said.

As of now, the inability to meet the road repair deadline exposes the unplanned execution of crucial public amenities projects. Significantly, the UP Jal Nigam, and Lucknow Municipal Corporation in an undertaking before the SHRC on May 26 had promised to get the roads repaired by June 15. A report was supposed to be submitted with the commission on June 30.

In fact, chief minister Mayawati too had directed the authorities to get the roads repaired latest by June 30.
 

Sankey Road widening to begin today

Print PDF

The Hindu        27.06.2011

Sankey Road widening to begin today

Staff Reporter

Residents of areas around Sankey Road in Bangalore have intensified protest andannounced that they will meet Deputy Mayorto sort out the issue.— Photo: K. Gopinathan
Residents of areas around Sankey Road in Bangalore have intensified protest andannounced that they will meet Deputy Mayorto sort out the issue.— Photo: K. Gopinathan

A day before the scheduled start of widening of Sankey Road stretch by the Bruhat Bangalore Mahanagara Palike (BBMP) on Monday, members of the Sankey Park Walkers Association intensified their agitation against the proposed widening by walking up to MLA C.N. Ashwath Narayan's residence to seek a review of the project.

However, Mr. Ashwath Narayan was not present. The green brigade will now meet Deputy Mayor S. Harish on Monday to register their reservation against the project with him, and ask him to stop the project till their concerns are addressed.

The association members, comprising residents of the areas around Sankey Road, have also launched an agitation against the proposed widening of the road between Bhashyam Circle and Malleswaram 18{+t}{+h}Cross Junction.

Apart from anger over felling of trees for widening, the association members also expressed displeasure over the manner in which some private property had been marked for acquisition allegedly without giving the owners any notice.

However, Mr. Harish had told presspersons here on Saturday that contrary to claims made by non-governmental organisations and a few resident welfare associations that over 500 trees will be felled on this stretch, only 19 trees will be felled.

He said that the Directorate of Urban Land Transport had studied the project proposal and stated that the stretch between Cauvery Junction and Bhashyam Circle need not be widened. This stretch is 27 m wide.

“The road is being widened as per the Revised Master Plan 2015. The passenger car unit per hour on the road is 3,637 and nearly 43,600 vehicles use the road every day. The work orders have been issued and work will be completed in 18 months,” he said.

Mr. Harish added that only four properties needed to be acquired. Contrary to claims of the NGOs, Stella Mary's school building will not be affected. Only the temporary shed on the premises will be brought down.

62 trees

He said that on the stretch between Sankey Park and Maramma Circle, 62 trees will be felled — 13 in Sankey Park and 49 on the Forest Department campus. The road width of this stretch is just 15 m and needs to be widened. The stretch between C.N.R. Rao Circle and Yeshwantpur Circle, which is 23 m to 25 m wide, will be widened to 45 m as per Revised Master Plan 2015.

 

Garbage piles up on city roads

Print PDF

The Hindu       07.03.2011

Garbage piles up on city roads

Staff Reporter

With the sanitary workers strike entering the sixth day on Sunday, heaps of garbage got piled up across the city. The Vijayawada Municipal Corporation , despite all its contingency plans, could clear only 300 metric tonnes (MT) of garbage.

More than half the workforce has not been turning up for duty.

The contingency plans seem to have not been successful as nearly 250 MT of garbage was left uncollected. The Vijayawada Municipal Corporation (VMC) could clear about 130 dumper bins in the city as against a total of 400 dumper bins.

The strike is being spearheaded by the CITU-affiliated Municipal Corporation Workers' Union.

The garbage on connecting roads, arterial and internal roads could not be cleared. It was glaringly evident in areas like Maruti Nagar abutting Eluru Road.

The city generates nearly 550 MT of garbage daily.

The six main demands of the union include regularisation of services of workers serving on a contract basis, approval of Rs. 6,700 as minimum wage, grant of 15 days casual leave, issue of identity cards, coverage under insurance scheme and talks between union leaders and Regional Director at regular interval to keep the higher-ups abreast of the problems.

 


Page 73 of 146