Urban News

  • Increase font size
  • Default font size
  • Decrease font size
Road Development

Road work at the mercy of encroachers

Print PDF

The Hindu 12.04.2010

Road work at the mercy of encroachers

S. Anil Radhakrishnan

Many violations along the Kowdiar-Marappalam-Pattom stretch

— Photo: S. Mahinsha.

Defiant stance:An encroachment near Kowdiar Junction that is preventing timely completion of storm water drains.

THIRUVANANTHAPURAM: Encroachments near Marappalam, Kowdiar and Pattom junctions are delaying the commissioning of the Kowdiar-Pattom road, which has been widened under the City Road Improvement Project (CRIP).

Residential apartment complexes at Kowdiar and Pattom junctions, a grocery shop near Marappalam, on the road leading to Pattom, and a jewellery shop near Pattom junction are encroaching upon the road, thereby stalling construction of storm water drains on these stretches.

An official of the Thiruvananthapuram Road Development Company Ltd (TRDCL), the implementing agency of CRIP, said the encroachment by the apartment complex had prevented it from constructing drains in a 60-metre stretch in Kowdiar junction and a 35-metre stretch in Pattom junction.

A ramp constructed in front of the apartment complex in Kowdiar is jutting 60 cm into the road. It should be dismantled to construct the drains and prevent flooding at the junction. After the TRDCL took up the matter with the Kerala Road Fund Board, a meeting convened at the highest level had decided to resurvey the plot and fix the boundary of the complex. “Somehow, it did not work out,” he said.

Before monsoon

The TRDCL, on Thursday night, commenced the tarring work on the Kowdiar-Kuravankonam road without constructing the drain near Kowdiar junction. The aim is to complete the works in the stretch before the onset of the monsoon. The drain will have to be constructed later along the 60-metre stretch and connected with the existing one on the Kuravankonam side. Only after the drain is constructed and the tarring work is done, can be the junction be modified.

Another hindrance is a cable drum dumped on the mouth of the Kowdiar-Pattom road, near the gate of the Salvation Army Higher Secondary School, by the Kerala State Electricity Board. It has remained there for several together.

Shop usurps space

In the road leading from Marappalam to Pattom, a grocery shop in the corner has encroached into the road. The TRDCL has alleged that the alignment of the storm water drain was altered by vested interests to protect the shop. “The workers were abused here,” the official said. A jewellery shop at Pattom is also a culprit.

Delay in completion of work by other utilities agencies has seriously hampered road work.

The Kerala Water Authority had not filled the trenches on either side of the approach road to the newly constructed Marappalam bridge. The Japan International Cooperation Agency (JICA), which is entrusted with a water supply project, has not constructed the valve chambers at Kuravankonam junction.

The shallow sewerage line in the stretch also needs to be shifted. “Once the KWA and other agencies complete their work, we can finish the Marappalam-Pattom stretch and open it for traffic within 10 days,” the official said.

Manholes in footpaths

The TRDCL has constructed manholes in footpaths every 60 metres and has laid pipes as per the KWA specifications to connect the manholes in footpath to the manholes of the KWA in the road.

So, those needing sewerage connections will not have to dig up the road.

They will just have to bring the connection of the sewerage line from the house to the manhole in the footpath.

Sewerage line is also being laid in the 800-metre stretch from Toll Junction to Ambalamukku to prevent further digging up of the stretch.

The TRDCL said they had taken the work as there is no sewerage line in the stretch and to avoid delay in completing the road widening works even though it was not part of the memorandum of understanding.

The TRDCL says they will need a minimum of one month for completing the finishing works like construction of footpath, laying of tiles along the footpath, planning of trees and for road signs along the one-km stretch after the road tarring work is completed.

Last Updated on Monday, 12 April 2010 07:15
 

Udupi-Manipal Road to be ready before monsoon

Print PDF

The Hindu 05.04.2010

Udupi-Manipal Road to be ready before monsoon

Staff Correspondent

Udupi: The second phase of the four-laning work of the Udupi-Manipal Road is likely to be completed before the monsoon.

Commissioner of Udupi City Municipal Council (CMC) Gokuldas Nayak told The Hindu on Sunday that under the second phase, the four-laning work was already in progress from Kadiyali in Udupi to Syndicate Circle in Manipal. As per the tender agreement, the road had to be constructed in 18 months at a cost of Rs. 12 crore.

“Alhough putting of the dividers and other small works may take some more time, the road is likely to be ready before the monsoon sets in,” he said.

The first phase of the four-lane Udupi-Manipal Road from Karavali Junction to Kadiyali had been completed and thrown open for traffic. Unlike the Karavali Junction to Kadiyali stretch, which is fully concreted, the Kadiyali-Syndicate Circle stretch would be asphalted, he said.

The CMC would be widening (two-lane) the stretch between Jodukatte and Ambalpady Road in this fiscal year. The four-laning of the Tangadagady-Kalsank Road would also be taken up in this fiscal, he said.

The CMC had already floated tenders for removing the silt from the roadside drains. The work was expected to begin within a week, he said.

Mr. Nayak said that only Dugli Padu and Manjushri Nagar areas in the city were facing drinking water shortage. This was because the drinking water from the Swarna River second stage was yet to be connected there.

People in this area were presently being supplied water from a borewell. Another borewell would be sunk soon in this area. Plans were afoot to construct an overhead tank in Manipal to supply water to these two areas, he said.

There was no shortage of drinking water in any other area of the city. No drinking water shortage was expected in the city during this summer as there was sufficient water in the Baje Dam, he added.

Last Updated on Monday, 05 April 2010 05:11
 

Gurgaon municipal body to repair, expand Jharsa Road

Print PDF

Indian Express 17.03.2010

Gurgaon municipal body to repair, expand Jharsa Road

Express News Service Tags : roads, delhi Posted: Wednesday, Mar 17, 2010 at 0116 hrs
New Delhi: The Gurgaon Municipal Corporation is all set to repair and expand the dilapidated and narrow Jharsa Road starting from Delhi-Gurgaon Expressway to Mor Chowk. The road will be made four-lane, offering a relief to the residents of Sector 15 Part-I and II, Patel Nagar, Friends Colony, Housing Board Colony and other adjoining colonies, Commissioner of Municipal Corporation Gurgaon Rajesh Khullar said.
“Map has been prepared for the widening work and the project is expected to cost over Rs 2 crore. Tenders for the work will be floated within 10 days,” he said.
Last Updated on Wednesday, 17 March 2010 10:59
 


Page 129 of 146