Road Development

PMC chief cracks whip to ensure quality of roads

Print PDF

The Indian Express             12.08.2013

PMC chief cracks whip to ensure quality of roads

As large number of potholes that surfaced on city roads raised doubts over quality of work done by the PMC contractors, the civic administration has decided to be cautious about the development work being done in the city.

Municipal Commissioner Mahesh Pathak has asked the heads of departments and contractors to submit justification for any work being done at 15 per cent below the estimated cost. The civic chief said a lot of development work is found to be allotted at 15 to 40 per cent below the estimated cost.

"If any work is allotted for less than 15 per cent below the estimated cost, the department head should give an explanation and the contractor should also provide the details," Pathak said.

The e-tender process of PMC has increased competition among contractors, but it is expected that the rates quoted by contractors should be close to the estimate cost worked out by administration, the directive said. "Below quotation indicates that the civic administration estimate is not as per the market rate. The estimates are not prepared as per the market rate or there is improper supervision of work to decide on quality and quantity of work done while paying the bill for the work."

Thus, to ensure proper estimate of the work and also maintain the quality, there is need to review the existing system, the civic chief said. "A meeting of technical committee should be immediately called to frame guidelines within a month on steps to be followed while allotting development work to contractors."

All civic departments should set up a vigilance system to ensure quality of work, as per the specifications in the tender. Third party inspection of work should be done and if need be head of department should inspect important civic work done through contractors, it added.

The site engineer should verify the quality of material used by contractor, along with the machinery as per the demand in the project estimate, the directive said. "If any violation is found, work should be stopped and action should be initiated against the contractor." 

 

Cement concrete roads to be laid at Kirana, Bande Bazaar

Print PDF

The Hindu               12.08.2013

Cement concrete roads to be laid at Kirana, Bande Bazaar

Special Correspondent

Estimated cost of the project increased to Rs. 3.2 cr.

Qamar-ul Islam, Minister for Municipalities and Local Bodies and Wakf, and district in-charge, has said that the design of the widened road of Kirana and Bande Bazaar leading to Nehru Gunj locality has been changed, and instead of a black topping road a cement concrete road with medians would be constructed.

The Minister, who chaired a review meeting of the development works taken up in Gulbarga city on Sunday, told The Hindu that the estimated cost of the road project has also been increased from Rs. 1.99 crore to Rs. 3.2 crore. As no contractor had come forward to take up the work, it has been divided into seven bids and fresh tenders would be floated. All the seven bids would be opened simultaneously and work awarded so tat all the seven works start simultaneously, and are completed on time.

To a question, he said that the work of the laying of the road would begin within three months. The meeting also gave its approval to the acquisition of the buildings on the Lalgiri Cross Road which had remained a bottleneck to take up the road-widening work there.

He said that out of the Rs. 200 crore sanctioned for Gulbarga city under funds granted for the Tier II cities for taking up infrastructure development projects, so far Rs. 145 crore has been released by the government. And, Rs. 5 crore was released a couple of days ago. The remaining Rs. 50 crore is the loan component which would be released in two instalments by the government. It is expected that Rs. 25 crore would be released within three months. The release of these funds would enable the authorities to complete the ongoing pending works taken up in the city.

To another question, he said that the State government in principle has also agreed to release Rs. 40 crore from the Rs. 145 crore released under the development of infrastructure facilities in the Tier II cities for the acquisition of the buildings for taking up road-widening works in Gulbarga. Once this fund is made available, other pending works could also be completed in Gulbarga.

On the bad state of roads in Gulbarga, Mr. Islam said that the meeting also decided to utilise Rs. 5.5 crore available with the government to fill potholes on a war footing.

A decision has also been taken to widen the existing four main roads in the city by paving concrete shoulders on both the sides of the existing roads to give more leeway for the easy flow of traffic and given an aesthetic look to the roads, he added.

 

NMC speeds up road repair work

Print PDF

The Times of India             08.08.2013

NMC speeds up road repair work

NASHIK: The public works department (PWD) of the Nashik Municipal Corporation (NMC), which began repairing city roads with the break in rains, has sped up the work and assured citizens that most potholes will be filled up within the week.

The department filled up 3,071 potholes with gravel and murum, 11,522 potholes with asphalt mix and carried out patchwork on 310 bad and uneven roads in July. Over 2,000 potholes in the six divisions of the city and some patchwork on its main roads remained in need of repair.

"Potholes are exposed due to the continuous rains even if they had been filled up earlier, thus this is ongoing work in the monsoons. With no rains over the past few days, we have sped up the work to cover as many potholes as possible," said an engineer of the PWD.

From August 1 to 5, a total of 366 potholes were filled in the east division; 108 potholes were filled with water-based-macadam (WBM) in Nashik Road, 17 trenches were covered, 220 more potholes were covered with gravel and murum and 223 trenches on road-crossings and 15 on the paver blocks were repaired.

"We have not yet compiled the data of how many potholes have been covered in the past two days, but the divisional offices have sped up the work, following number of complaints from people. Most of the divisions are refilling already repaired potholes, which were exposed due to continuous rains," said a senior PWD official.

 