The Indian Express 03.09.2012
BMC files caveats to prevent stay on demolition drive
As the civic body prepares to clear over 8,000 shanties from the
city’s footpaths, officials have, in order to preempt any delays in the
demolition, filed over 1,200 caveats in various city courts over the
past weeks. The caveats were filed to ensure that courts do not pass
stay orders without hearing the BMC.
The Brihanmumbai Municipal Corporation (BMC) is aiming at
October, what they consider the most ‘practical’ month, to launch much
delayed but highly ambitious Mahatma Gandhi Path Kranti Yojana. Under
this scheme, the BMC was to make city’s pavements encroachment-free and
relocate the squatters. An estimated 25,000 pavement dwellers were
identified under the project in 2006 but the project been delayed due to
legal hassles, said civic officials.
Aseem Gupta, Additional Municipal Commissioner, said, “Typically,
when we send eviction notices to these pavement dwellers, they approach
a court and get a stay order. But after the caveats are filed, the
court cannot stay the demolition orders and will have to first hear our
side”.
“We are waiting for the monsoon to end, after which we will begin
removal of these encroachments. We plan to complete the project within a
month, after which it will be festival season when there will be a lot
of opposition to the drive, said Gupta.
It is difficult to undertake demolition activity in November,
December and January as these are festival months, after which March is
usually examination time for students. With June, July and September
being the monsoon season, it is difficult to remove families from their
homes, said officials. Of the 8,000 families to be rehabilitated, only
4,000 will be allotted alternative accommodation by MMRDA . The rest do
not fulfill the eligibility criteria of 1995, said officials.
Under the project, which has been clubbed with the road-widening and
construction project, the BMC will clear around 2,000 structures between
Sion and Mulund in the first phase. A compensation policy has already
been devised by the BMC, under which either monetary compensation at the
ready reckoner rate of the land value or other alternative
accommodation will be provided by the civic administration. The civic
body has kept aside Rs 300 crore for such projects.
The civic body had identified over 75 pavements and roads to be
made encroachment-free. These include Senapati Bapat Marg, Barrister
Nath Pai Road, P D’ Mello Road, Tulsi Pipe Road and Zakaria Bunder Road.