Urban News

  • Increase font size
  • Default font size
  • Decrease font size
Urban Infrastructure

Canal planned to drain floodwater from city

Print PDF

The Hindu         14.03.2011

Canal planned to drain floodwater from city

Staff Reporter

Trial digging for the drain will begin soon

Pending work: The flanks of the Sahodaran Ayyappan Road have been left unattended after the relaying of the stretch. — Photo: H. Vibhu
Pending work: The flanks of the Sahodaran Ayyappan Road have been left unattended after the relaying of the stretch. — Photo: H. Vibhu

Trial digging for a major canal for diverting floodwater from the city will begin shortly. The civic authorities are planning to construct a major drain from near the Medical Trust Hospital junction through Arun's Corner on MG Road to Warriam Road and from there to the Kochi backwaters for draining the floodwater.

As several underground oil pipelines have been laid in the area, trial digging will have to be carried out before initiating the canal work, said Soumini Jain, chairperson, works standing committee, Kochi Corporation.

This is the shortest route to drain the floodwater from the city to the Kochi backwaters. The canal could be constructed through this route without taking much turns and curves. This would ensure unhindered flow of floodwater through the drain, freeing the city of water logging to a considerable extent, she said.

As important thoroughfares would have to be cut open for digging the drain, vehicular movement in the area might be affected partially, she said.

The laying of tiles on the flanks of the Sahodaran Ayyappan road would commence after the completion of the drain work. The road had been re-laid at a width of 7.5 metre each on both sides of the median leaving the flanks unattended. The construction of the drains on the flanks of the road could be undertaken after clearing the cables laid by various service providers in the area. The Kochi Corporation had been coordinating these for the purpose, Ms. Jain said.

Ms. Jain said that most of the city roads had been repaired and made motorable using the plan fund of the corporation. The repair work of almost all major roads was completed and some were in the final stages. All the works implemented using the plan fund would have to be completed before March 31, she said.

Chittoor road

The repeated efforts of the Kochi Corporation to take up the relaying of the Chittoor road failed as there were no takers for the work. The tender for the Rs.52-lakh work was floated twice but no one came forward for taking it up. However patchworks were carried out on the road to make it motorable. Efforts were being taken to get the work included in the Jawaharlal Nehru National Urban Renewal Mission project. A proposal for relaying the stretch with a five-year guarantee was also under the consideration, she said.

As the model code of conduct was in force, the initiation of new projects would be possible only after the Assembly election.

The corporation had been focusing for completing the works that were cleared earlier, she said.

 

City’s electric crematoriums defunct, may work by April

Print PDF

Deccan Chronicle       03.02.2011

City’s electric crematoriums defunct, may work by April

February 3rd, 2011

Hyderabad, Feb. 2: It has been a year since the two electric crematoriums of the city died a silent death and it doesn’t seem that they will be resurrected soon.

The two facilities — at Bansilalpet in Secunderabad and at Amberpet — are unlikely to be operational before April and many families arriving at the crematoriums to perform the last rites of their kin are returning disappointed.

Such families have no other option but to go to the traditional cremation grounds as a result of which the load is increasing on the Shamshana Vatikas.

Recently, a family was made to wait for eight hours at Amberpet Shamshana Vatika for cremation rites as there were four bodies queued up for the ritual.

“It’s not only taking a longer time at the traditional shamshana vatikas but it is also an expensive affair. While it was `150 at the electric crematorium, the rates go up to `2,000 in the traditional shamshana vatikas including `1,200 for wood and labour charges,” said Mr Pradeep Kumar, a resident of Moosaram Bagh.

Officials of the Greater Hyderabad Municipal Corporation said that the two electric crematoriums had been shut down by the civic body a year ago for the upgradation and to add two more electric furnaces to increase their intake capacities.

However, they were silent when asked whether a notification had been given in the newspapers informing the people about the closure of the two facilities.

The GHMC executive engineer, Mr Shiv Raj, said there were complaints from local residents that the outdated electric equipment was emanating smoke and foul smell.

“We shut the two facilities as part of an overall project to construct two new electric crematoriums, and for upgrading the two facilities at Bansilalpet and Amberpet. Chennai-based Essco Furnaces Private Limited is executing the project and at least two facilities will be commissioned by the end of April,” said GHMC superintending engineer, Mr P. Peetambara Rao.


 

MCD deliberative wing to shift to new civic centre by February

Print PDF

The Hindu      24.01.2011

MCD deliberative wing to shift to new civic centre by February

Manisha Jha

After the near completion of the shifting process of the Municipal Corporation of Delhi's executive wing, the civic body's deliberative wing is gearing up to shift there next by February first week, according to Delhi Mayor Prithvi Raj Sawhney.

“Since the shifting of the executive wing from the MCD headquarters in Town Hall is more or less complete, the deliberative wing comprising the office of the Mayor, Deputy Mayor and Standing Committee chairman would be shifting by the first week of February. We have already communicated to the Municipal Commissioner to complete all arrangements including furniture, sound and light fittings, security and phone and intercom connectivity in the building by that time,” he added.

The Mayor further stated that the delay in readying of the two meeting halls constructed in the new civic centre was caused by a hold-up on part of the United States suppliers of equipment in view of their festive season.

“The lights and sound fitting equipment for the two halls was to come by January from US-based firms as we had placed our orders in December. However, owing to Christmas festival in December they stopped work for almost a month there leading to delay. The equipment is now expected to come in February and accordingly the two halls should finally be functional by March end. Till then the meetings of the MCD House and Standing Committee would take place at Town Hall only,” he added.

MCD Leader of House Subhash Arya also stated that only the offices of the engineering department and of the additional commissioners falling under the executive wing were still remaining to be shifted to the new civic centre along with the deliberative wing.

However, the Mayor admitted to several glitches still to be ironed out before the shifting process could come through to the new civic centre located on Minto Road.

“There is still no canteen in the new civic centre and the mobile phone connectivity is only limited till the 17 {+t} {+h} floor instead of up to all the 28 floors. So if we try to call officials who sit on floors above the 17 {+t} {+h} we are unable to reach them. We hope these problems would get sorted out by the first week of February so that the shifting takes place smoothly,” he added.

 


Page 89 of 181