Urban News

  • Increase font size
  • Default font size
  • Decrease font size
Water Supply

Four lakh new meters installed in last six years, says Delhi Jal Board

Print PDF

The Hindu                31.05.2013

Four lakh new meters installed in last six years, says Delhi Jal Board

Staff Reporter

Order placed for four lakh more: DJB

The Delhi Jal Board (DJB) has refuted the claims of NGO Citizen’s Front for Water Democracy that the water utility is procuring more meters than it needs to. In a statement issued here, the Board dismissed these allegations.

“The figures given by the NGO are misleading, baseless and mischievous. In fact, the DJB has procured and installed four lakh domestic water meters over the last six years [2005-2011]. At present the Jal Board has about 19.81 lakh registered consumers, of which 14.2 lakh are metered. In order to encourage metering of water consumption, the Board allows its consumers to procure and install their own ISI-marked meters. However, around 40 per cent of the meters installed by the consumers are found to be either deficient or non-functional. Therefore, the Board decided to procure and install, at its own cost, good quality meters with built in operation and maintenance of five years for metering of water consumption. This is expected to improve water auditing and encourage responsible and equitable consumption of water,” the DJB statement read.

It went on to add that the Board has recently placed an order in April 2013 for procurement of four lakh more meters with built-in operation and maintenance of seven years. “This order is now under implementation. It needs to be mentioned in this context that the Jal Board also expects the consumer base to increase rapidly because new, planned and unplanned areas have been connected with piped water supply network. This requires the Board to be equipped with adequate number of meters in order to ensure that newly sanctioned water connections are metered right from inception.”

For the Chandrawal project, which envisages the rehabilitation of not only the oldest water treatment plant but also its command area, the detailed project report is under preparation and no requirement for meters has been finalised yet. “It should also be mentioned that the replacement of meters is a continuous process since all meters have a certain life cycle. The Board’s endeavour is to continuously expand its connection base and ensure that all connections are provided with accurate meters.”

The NGO had claimed that the DJB was procuring at least 14,29,400 meters, whereas there were only 3,51,000 unmetered connections.

 

Pipe-laying to be completed by July, says P J Joseph

Print PDF

The New Indian Express                 30.05.2013

Pipe-laying to be completed by July, says P J Joseph

The laying of the new 1,219-mm main pipeline to replace the old, leak-plagued one, will be completed by the first week of July, Water Resources Minister P J Joseph said on Wednesday.

The KWA also has announced that the work will, in all likelihood, be completed well ahead of the September deadline, the Kerala Water Authority (KWA) said on Wednesday.

 The pipe is being laid from Aruvikkara, where the KWA pumping station is, to Peroorkada in the city. So far, the mild-steel (MS) pipe has been laid over 3.5 km, KWA Chief Engineer (distribution - south) Sreekumaran Nair said. The water utility has time till September 4 this year to complete the work, but it should be completed well ahead of the deadline as the work is progressing - including the water and air tests - fast, he said.

 There were reports that the project could be delayed, which prompted the KWA to come out with a clarification on Wednesday to ‘allay the fears’ of the public, the KWA said.

 The work has been awarded to M/s Laxmi Civil Engineering Service Pvt Ltd and the pipes are being supplied by Jindal SAW, the KWA said. 

In addition to quality checks by the company, the KWA also has entrusted ITENG Engineering, Mumbai, to conduct the checks as prescribed by ISI. The tenders for the project were invited on the advice of WASCON, the design unit of KWA, as per guidelines set by the CPHEEO Manual, KWA officials said.

 The MS pipe will be laid for a total of 9.695 kilometres to replace the old pre-stressed concrete pipeline on which the city depends for drinking water.

 The new pipeline is expected to solve the water supply woes of the capital city, which has been affected on multiple occasions in the past few months owing to leaks developing on the existing concrete pipeline.

In fact, the government has also announced a project to replace all the old pipelines within the capital city also.

 

Hogenakkal water for parched dts

Print PDF

Deccan Chronicle                  30.05.2013

Hogenakkal water for parched dts

Chief minister Jayalalithaa examines photographs displayed on Hogenakkal water supply and fluoride mitigation scheme at the secretariat after launching the project. 	—DC
Chief minister Jayalalithaa examines photographs displayed on Hogenakkal water supply and fluoride mitigation scheme at the secretariat after launching the project. —DC

Chennai: It was a dream come true for thousands of water-starved and flouride-affected people of  Dhar­mapuri and Krishnagiri districts as chief minister Jayalalithaa on Wednes­day inaugurated the Rs 1,928 crore Hogenakkal Combined Water Supply Scheme, nearly five de­cades after it was conceived. While taking pri­de for launching the scheme, she blasted DMK leader Stalin for alleging that the scheme had fallen behind schedule.

Inaugurating the water project, through video-co­nferencing from the  secretariat here, the CM said she was delighted to lau­nch the dream project of the people of Dharma­puri and Krishnagiri districts. “I feel proud to la­unch this much-awaited Rs 1,928 crore scheme,” she said.

The CM also hit out at DMK treasurer Stalin for his ‘malicious’ campign al­leging that the AIAD­MK had de­layed the sc­heme and he could complete it in two months if given the chan­ce.

Recalling that a DPR was prepared for implementing the project when the late MGR was the chief  minister in 1986, she said, “During my first tenure a  project report was prepared for the sc­heme in 1994, but could not be implemented owi­ng to lack of funds.”

Wh­en she assumed power for second time, a revised pr­oposal was sent to the Ce­ntre in August 2005, after including few more areas with Rs 1,500 crore financi­al aid from JICA. “After that, the foundation stone was laid in 2008 for the pr­oject, which tri­ggered pr­o­tests from the Karna­taka unit of BJP. Against this, I had ann­o­unced a pr­­otest on Aug­ust 26, 2008.” 

Following this, a resolution seeking Centre’s ass­itance to TN was adopted in the Assembly. But wi­th­out informing the Ho­use, the then CM M. Ka­r­u­nanidhi annou­nced ho­l­d­ing the project till a new government in Karn­ata­ka assumed offi­ce aft­er assembly polls. “I tried to raise the issue in the As­sembly but was not permitted. By 2011, when the AIADMK took over, 50 per cent of the work sh­o­ul­d have been completed but only 18 per cent was done”, she said. 

Project faced many bumps before fruition

Krishnagiri: The Hogenakkal drinking water project (HDWP) implemented to provide safe drinking water to the fluoride-affected Dharm­apuri and Krishnagiri districts crossed several hurdles before its inauguration on Wednesday.

The locals said the first proposal for the project came in 1960 when K. Kamaraj was the chief minister. In 1996, the project took shape with financial assistance from Japan international cooperation agency (JICA). But this was dropped after international sanctions following the Pokhran nuclear blast in 1998.

HDWP was re-started after the countries lifted the sanctions. JICA again came forward to offer loan for HDWP but the project was opposed by neighbouring Karnataka, against its approval in May 1997, allowing Tamil Nadu to use Cauvery for drinking water purpose.

In March 2008, former Karnataka chief minister B.S. Yeddyurappa was the first to raise his voice against the project for political reasons and claimed that the site for the headworks of HDWP, along the course of the Cauvery in Hogenakkal, belonged to Karnataka.

Yeddyurappa’s claim sparked controversy and tension in both states. The claim was later followed by other political and pro-Kannada movements and worsened the relationship between the two states.

With works at HDWP held up, Tamil Nadu sought the Union government’s intervention for smooth implementation of the project. But, Yeddyurappa, after becoming Karnataka’s CM, gave the green light for HDWP.

The works for the project were done on a war-footing with 2012 December as the deadline to complete the project. But, the works were delayed for other reasons giving room for the opposition to comment that the ruling AIADMK was shelving HDWP because the foundation stone for the project was laid in February 2008, during the DMK rule.

On Wednesday, the police had made elaborate security arrangements across Dharmapuri and Krishnagiri to prevent group clashes following the poster war between the AIADMK DMK over the project. The AIADMK members’ posters thanked the chief minister for completing and inaugurating the project when people in Dharmapuri and Krishnagiri were facing water shortage.

Time for celebration in two districts

Dharmapuri: Several thousands of people watched as chief minister J. Jayalalithaa, on Wednesday, inaugurated the Hogenakkal drinking water project to provide safe drinking water for the fluoride-affected Krishn­agiri and Dharmapuri districts.

Krishnagiri and Dharmapuri districts had made elaborate arrangements following the inauguration from Chennai, using video-conferencing facility.

In Dharmapuri, the function was held in Ambedkar nagar, with the participation of collector R. Lily and others. A similar function was held in Dinnur village of Hosur in Krishnagiri in the presence of collector T.P. Rajesh and others.

Several lakhs of people in Dharmapuri and Krishnagiri welcomed the move in their villages by bursting crackers and distributing sweets immediately after the inauguration and subsequent release of water from overhead tanks meant for the project.

Many villagers also organised special pujas in temples and other places of worship following the arrival of Cauvery water here. The arrival of the river water to Dharmapuri and Krishnagiri is significant as the river was of no use to them before the Hogenakkal drinking water project and also due to the obstacles faced by the project since 1996.

The project was implemented at a cost of Rs 1,928.80 crore, received as loan from Japan international cooperation agency (JICA), to provide safe drinking water.

TWAD sources said the Cauvery water is pumped from a height of 1,150 metres from headworks along the course of the river in Hogenakkal to reach Madam of Pennagaram.

From Madam, the water is treated and transported to Dharmapuri and Krishnagiri using pipelines laid to a distance of 9,965 kilometres for the project.

HDWP will deliver 128 mld of water for 30 lakh people but the project is designed with a capacity of 160 mld to meet the requirements of the expected 45 lakh population in the next 10 years.

 


Page 82 of 414