Urban News

  • Increase font size
  • Default font size
  • Decrease font size
Water Supply

Now, a water pipeline delays BMC’s trauma centre project

Print PDF

Indian Express        10.11.2010

Now, a water pipeline delays BMC’s trauma centre project

Pritha Chatterjee Tags : BMC, trauma centre project Posted: Wed Nov 10 2010, 06:04 hrs

Mumbai:  The BMC’s ambitious 265-bedded trauma centre project in Ajgaonkar, Jogeshwari, has been consistently delayed owing to a variety of reasons. The latest hurdle, according to sources in the BMC’s city engineering department, was a 1200-mm water pipeline that was found while digging the ground for constructing the basement of the centre. The officials said the project had been further delayed since the design of the structure had to be changed owing to this.

“The pipeline was found after digging a few feet. Representatives from our department had a war of words with the health department. The plot should have been properly scrutinised before passing an order for a 14-storey structure,” a senior engineer said. “There was no other solution. We had to shift the foundation by around six metres,” he said.

According to him, the deadline set for two years from August 2009, has been delayed by at least eight months owing to changes in the design. He said construction activities had to be postponed, as the work order for the project came just before the onset of the monsoon.

“Work was delayed by almost four months, as we had to constantly reschedule deadlines because of the rains,” an engineer said. As per the project’s financial records, over Rs 40 crore has already been sanctioned. The total estimated budget for the project is Rs. 97,32 18,509. Now, engineers say several problems has arisen while selecting a plot for the hospital. 

“Only one acre land has been allocated for the project. It is so close to the highway. Hence, construction activities can only be carried out at nights,” he said. The project is also “dangerously” close to an SRA building, he said. According to the official, after the changes in design, construction activities have been more swift. “Work on the second floor of the building should have been started by now. So far, only the ground floor and basement have been completed. But now we are progressing at a steady pace,”said the engineer.

Even though a schedule was prepared formally in 2008, tenders were invited only in April 2009. Sources said the standing committee had given its approval for the project in 2006. “The project has seen a delay up to three years. Now, new problems are emerging,” said a senior civic official. “ Despite these, we aim to meet the original deadline. The project has been expanded phenomenally from the original plan,” said medical superintendent of peripheral hospitals.

Corporators, however, say the original deadline for the project—October 2011— seems to be too ambitious . “We will also need more funds. The trauma centre has now been expanded to house other facilities like maternity and pediatric wings,”said health committee chairman Ashvini Mate.

Last Updated on Wednesday, 10 November 2010 09:58
 

Civic body to monitor your daily water supply

Print PDF

Hindustan Times  09.11.2010

Civic body to monitor your daily water supply

Soon, the Brihanmumbai Municipal Corporation (BMC) would know the exact amount of water you receive at home.  To plug water leakage and theft, the civic body will install flow metres on various reservoirs and pipelines under the new water management system.  By next year, the BMC would know the exact amount of water that end users consume and the amount that is wasted via leakage and theft.

In the first phase of the project, the civic body will install about 300 flow metres at the cost of Rs 160 crore, of which over 150 have already been installed at 30 reservoirs and on few water mains. “The remaining work will be completed in the next three months up to January 2011, and in a year, every household would come under the BMC scanner, after installation of flow metres,” said Rahul Shewale, chairman of the civic standing committee.

As per the civic water department, more than 20% water that is supplied to the city on a daily basis is lost to theft and leaks. In the past one year, the BMC has repaired more than 35,000 leaks and has also accepted that there is more work to be done.

The civic body supplies 3,350 million litre daily (mld) water, while over 700 mld is wasted to leaks and theft.

The second phase of the project will involve the civic body fixing flow metres for bulk consumers and in the third phase, all 3.5 lakh residential consumers will be monitored with help of flow meters.

The flow metres would also help improve the water distribution system, which has been disturbed since a month. Two weeks ago, city corporators had decided to study the water distribution system in Mumbai and make recommendations for equitable water supply as per the population density in different wards.

A nine-member sub-committee, headed by Shewale, undertook the study. However, complaints about water shortage continued to pour in from certain parts of the city. The worst affected areas are those at the tail end of the distribution system.

Last Updated on Tuesday, 09 November 2010 11:03
 

PCMC water supply project hits a roadblock

Print PDF

The Times of India                   09.11.2010

PCMC water supply project hits a roadblock

PUNE: The Pimpri-Chinchwad Municipal Corporation's (PCMC) ambitious water supply project -- laying a 36-km pipeline from the Pavana dam to Nigdi -- has received an extension from the state government till December 2011. However, faced with severe opposition from residents in many villages from where the pipeline is to be laid, the future of the project hangs in balance.

Speaking to TOI on Saturday, Ambadas Chavan, joint city engineer and chief of water supply department, PCMC confirmed the extension of the deadline. Chavan said, "The work of laying the pipeline in the municipal limits on a stretch of around five km has been completed so far. The PCMC has received possession of 60 per cent of the land that is required for the project outside the municipal limits."

The extension was necessary as it is a Jawaharlal Nehru National Urban Renewal Mission (JNNURM)-funded project, said officials. PCMC had pointed out to the state government that the project has been delayed due to delay in getting land for the project.

P G Nale, special land acquisition officer, PCMC said, "The work of land acquisition on a 13-km stretch of the pipeline has been allotted. The villages in which land is to be acquired include, Donje, Shirgaon, Somatne, Parandwadi, Urse and Adhe. Land acquisition in five villages except Urse has been completed, he said.

Gajanan Babar, Shiv Sena MP from Maval Lok Sabha constituency, who has opposed the PCMC project said, "Our opposition to the project is due to two reasons -- the water flow in the river will later reduce and the power generation of the dam will stop. The municipal corporation will be constructing two Kolhapur type weirs on Pavana river to ensure that there is water throughout the year in the river. The lifting of water directly from the dam will stop generation of power as there will be no release of water from the dam."

Dnyaneshwar Dalvi, former president, Maval unit of BJP said, "The pipeline will pass through 75 villages. The water supply schemes and the 14,000 acres of irrigated land in these villages is completely dependent on the water released from Pavana dam into Pavana river. This was not taken into consideration while approving the project. Ten MW electricity is generated from the water released from the dam which will stop after the completion of the project."

He added, "PCMC should take water from Ravet bund on Pavana river instead of laying the pipeline."

District president of the Bharatiya Kisan Sangh (BKS) Shankarrao Shelar said that the sangh is considering approaching the Supreme Court as the project is against the interests of farmers and the residents in the villages. "PCMC should lift the water from Pavana river at Ravet or Gahunje villages. The cost of the project has escalated from Rs 400 crore to Rs 550 crore in two years and is expected to go up to Rs 1,000 crore. Only the future population of PCMC limits and its needs has been taken into account while considering the project. The population of towns and villages is also expected to increase by 2031, but it has not been considered."

Rajendra Kate, opposition leader, PCMC said, "The completion date has expired. PCMC should have given the work order for the project after getting all the requisite land in its possession. Many projects in PCMC cannot be completed due to non-availability of funds. If PCMC is going to reinvite bids for the project then it should invite bids after getting all the requisite land in its possession."

Mayor Yogesh Behl had demanded that the Pimpri-Chinchwad New Township Development Authority (PCNTDA) should bear the expenditure of the pipeline project by giving Rs 200 crore to PCMC as the residents of PCNTDA limits use the drinking water purified and supplied by PCMC. But, PCNTDA rejected the demand citing the reason that it cannot give money for such projects.

 


Page 223 of 414