Urban News

  • Increase font size
  • Default font size
  • Decrease font size
Water Supply

Woes galore in Rajagopalanagar

Print PDF

The New Indian Express  05.10.2010

Woes galore in Rajagopalanagar

Open drains pose a safety and health hazard to residents of Rajagopalanagar ward.

BANGALORE: The residents of Rajagopalanagar ward want the Bruhat Bangalore Mahanagara Palike (BBMP) authorities to pressurize the Bangalore Water Supply and Sewerage Board (BWSSB) to ensure regular supply of drinking water.

Majority of areas of Rajagopalanagar ward face acute shortage of drinking water. Some people were seen carrying water in plastic pots from distant places. Private water suppliers are exploiting residents by demanding premium amount. “We are facing lot of problems due to the shortage of drinking water here. We have to buy water by paying ` 2 per plastic pot,’’ says R Mohan, a resident.

Most of the drains are either filled with silt or choked with debris. For example, a concrete slab on an open drain was damaged a few weeks ago but the BBMP authorities are yet to replace the same. “No one has attended to the problem even after four weeks. It will be difficult for motorists to use this road at night,’’ said K Rashmi, a resident.

The other problem is the lack of underground drainage (UGD) facility. The residents have to dig up pits for sanitary purposes. Due to the lack of UGD facility, the residents let waste water into open drains. “We have to spend Rs 2,000 once in three months to clean pits. We request the BBMP authorities to pressurize the BWSSB to provide UGD facility in this area,’’ says Jayamma, a housewife.

The residents also face several problems due to mosquito menace. Many of them are suffering from fever. “The open drains have become a breeding place for mosquitoes. The BBMP authorities have not yet done anything to solve this problem,’’ says a housewife on anonymity.

Meanwhile, H N Gangadhara, corporator, has said that the `110-crore underground drainage work has been assigned to L&T. “The work will commence within 10 days. The work was supposed to commence a few weeks ago but was delayed to avoid inconvenience for the residents during monsoon,’’ said Gangadhara.

On the acute shortage of drinking water, the corporator says Rajagopalanagar ward is yet to get the Cauvery water supply. “Thirteen borewells were dug up to mitigate water shortage at this ward. Efforts are being made to improve the water supply. As of now the water is being supplied three days in a week,’’ the corporator said.

Last Updated on Tuesday, 05 October 2010 11:33
 

Work begins to bring 40 MGD potable water to Mohali

Print PDF

Indian Express   05.10.2010

Work begins to bring 40 MGD potable water to Mohali

Nitin Jain Tags : GMADA, MGD, Bhakra main line Posted: Tue Oct 05 2010, 03:20 hrs

Mohali:  Work has finally begun to quench the thirst of Mohali by bringing 40 MGD (million gallon daily) water from Bhakra main line (BML) in Kajauli to the district.Greater Mohali Area Development Authority (GMADA) has floated tender to invite bids from the interested contractual agencies to execute Phase V and VI of Kajauli waterworks scheme at an estimated cost of Rs 335 crore within three years.

GMADA will hold a pre-bid conference here on October 11 to answer the queries of the interested firms before submission of complete pre-qualification bid till October 19 when the received bids will be opened to shortlist the most eligible firm offering to work at minimum cost, a senior GMADA official told Newsline on Monday.

While according a formal nod to the project last month, Department of Housing and Urban Development had decided that under Phase V and VI of the scheme, only single pipeline of double size/capacity capable of supplying 40 MGD water would be laid instead of two separate pipelines of 20 MGD water capacity each as were laid in the presently functional four phases.

GMADA will execute the work and the expenditure will be met from funds available under the external development charges (EDC) recovered from the promoters of mega projects besides GMADA’s own sources. Land required for laying the pipeline is already available.

A committee, constituted for the selection of site for water treatment plant and pumping station at Mohali, has suggested few sites, among which the most suitable will be selected shortly. 

Work pertaining to the laying of pipelines under phase V and VI and construction of pumping station at Kajauli will be undertaken immediately in view of the land being available while acquisition of land for water treatment plant and pumping station at Mohali will be initiated simultaneously.

A joint scheme mooted earlier by Punjab government and Chandigarh Administration provides for laying six pipelines bringing 20 MGD water each from the BML to waterworks in Sector 39, Chandigarh. The scheme provides that four pipelines were meant to supply water (80 MGD) to Chandigarh and the remaining two pipelines will be laid for supplying water exclusively to Mohali. The cost of land acquired for this purpose was also shared accordingly by Chandigarh Administration and Punjab.

While Chandigarh Administration had contributed two-third of the land cost, Punjab’s share was one-third. A 50-feet-wide strip of land was acquired initially for laying six pipelines of 20 MGD capacity each from Kajauli to Chandigarh waterworks. Four pipelines of Chandigarh’s share have already been laid and the remaining land was meant for Punjab’s share of 40 MGD through two pipelines to be laid, divulged the release.

Since Chandigarh does not have any share in water available/running in BML, Punjab and Haryana were being given 2.5 MGD and 1.5 MGD water, respectively, from each pipeline laid by Chandigarh Administration. Accordingly, Mohali got 10 MGD water from the existing four phases of Kajauli waterworks. At present, Mohali gets 13 MGD water against its requirement of 23 MGD as compared to Chandigarh being supplied MGD against requirement of 70 MGD.

Last Updated on Tuesday, 05 October 2010 11:23
 

Work on new water pipeline begins

Print PDF

The Hindu  05.10.2010

Work on new water pipeline begins

 Staff Reporter

This will enable the GMC to augment water supply by 40 MLD

69 tankers pressed into service to provide water to residential areas

Work begins by inter-connecting the old pipeline



BIG TASK:Works connecting the second pipeline carrying water from Takkelapadu filtration plant to HLR reservoir going on at Sitarama Nagar in Guntur on Monday.

Guntur: Guntur Municipal Corporation on Monday began a mammoth engineering exercise of replacing the existing worn out drinking water pipeline with a new one.The pipeline was laid from Manipuram Railway over Bridge (RoB) to Nehru Nagar paving the way for laying of approach road to Manipuram RoB towards NTR Bus Station Complex.

The laying of new pipeline would enable GMC to augment water supply by 40 MLD. The city now gets a supply of 115 MLD. The pipeline measuring 1,200 mm dia extending to a length of 865 metres was being laid at a cost of Rs.1.83 crore.

The GMC suspended water supply to areas falling under High Level Reservoir (HLR) from Monday morning and the water supply is expected to resume on Wednesday. The GMC pressed 69 tankers into service to provide water to residential areas.

The engineering department of GMC began the exercise by inter connecting the old pipeline at five places. Workers dug up the roads and inter connected the joints at Padmaja Petrol Bunk near Manipuram RoB, at two places at Sitanagaram and two places at Nehru Nagar railway crossing. Inter connecting the pipeline with cement castings on both outside and inside was a difficult exercise and tested the patience of the workers. The works would be carried on Wednesday too.

Municipal Commissioner A Sarath inspected the works twice in the morning and asked the officials to be on their toes. Municipal Engineer Upendra Singh supervised the.works

The GMC had already laid the second water pipeline from Takkellapadu raw water source to filtration plant. The pipeline extends to a distance of 3.5 k.m.

Filtration plant

With the laying of second water pipeline, the filtration plant would start functioning to its full capacity of 90 MLD. The city gets 25 MLD of water from Sangam Jagarlamudi plant and 5 MLD from Vengalayapalem.

Last Updated on Tuesday, 05 October 2010 09:37
 


Page 245 of 414