Urban News

  • Increase font size
  • Default font size
  • Decrease font size
Water Supply

Jakkalamadagu water in a year

Print PDF

The Deccan Herald  04.08.2010

Jakkalamadagu water in a year

Chikkaballapur, August 3, DHNS:

 

“The contractor has been directed to complete construction of the dam by the end of this year. The work should have been completed by July end this year. The delay has resulted in escalation of the project cost from  Rs seven crore to Rs 14 crore,” the Deputy Commissioner said on Tuesday. He was speaking to reporters during the visit of of Doddaballapur legislator J Narasimhaswamy to inspect the progress of the work.

The MLA said the contractor has failed to execute the work within the stipulated time causing delay. He warned that action will be initiated against the contractor if the negligent attitude persists henceforth.

Bescom blamed

He said there has been considerable progress in the project and hence it had become impossible to even assure people on the completion of the project.

Assistant Executive Engineer Ranganath said the work has been delayed as Besom has not taken steps to remove the poles wherever required in spite of repeated requests.
The officers of Bescom though visited the spot and promised to remove the poles, have not carried out the work till day. On the other hand, residents of some villages objected to cutting off road connectivity for the project.

The project would go off smoothly if steps are taken to resolve these problems, he said.
The dam, if constructed in an extent of 3.5 square km, can store 4,300 million litres of water with which the City could be fed for at least seven months. The engineer said the recent heavy rains too have been hampering work. The work comes to grinding halt for one week even if it rains for a week. The work would gain pace after October, he said.
Ranganath sought the intervention of Deputy Commissioner for shifting of electrical poles and to convince the villagers of the need for the project.

City Municipal Council president B A Lokesh Kumar, councillors and others were present.
Last Updated on Wednesday, 04 August 2010 11:11
 

Very little water in TG Halli

Print PDF

The New Indian Express 04.08.2010

Very little water in TG Halli

 

BANGALORE: Though incessant rains have been reported from various parts of the state in the last week, the water level in the Thippagondanahalli reservoir (TG Halli reservoir) has not gone up even by a single foot.

There was only 10.6 feet of water in the dam on August 2. The dam can store up to 72 feet of water.

Last year, there was 33 feet of water in the dam on the same date.

According to data available with the Bangalore Water Supply and Sewerage Board (BWSSB), only six inches of water has flowed into the TG Halli dam till August 2 during this rainy season.

“The TG Halli catchment areas have not received adequate rain and normally a lot of water flows into the dam during August and September,” said BWSSB chairman PB Ramamurthy.

 At present, BWSSB is pumping 15 MLD of water to the city from TG Halli dam though it has the infrastructure to pump 125 MLD of water every day.

It is pumping nearly 900 MLD of water from all the four stages of Cauvery drinking water project, though it has a capacity to pump only 810 MLD. “The demand for water is increasing by the day and we are able to meet the demand due to the efficient distribution management of our officers,” said Ramamurthy. “It will be very difficult to meet the demand if TG Halli does not receive adequate water.”

BWSSB has already altered its method to treat water that is pumped from TG Halli reservoir as the turbidity level increases if the water level recedes beyond a level.

Last Updated on Wednesday, 04 August 2010 08:00
 

No funds to cut illicit lines

Print PDF

The Deccan Chronicle  04.08.2010

No funds to cut illicit lines

Officials said that the board needs at least Rs 2,000 to dig up lanes and by-lanes to disconnect one illegal line and then repave the roads again.

Because of paucity of funds, the board is allowing the illegal water connections to stay on though it is resulting in the loss of hundreds of crores of rupees to the exchequer.

The minimum water charges per year for the 30,000-odd connections work out to Rs 3 crore. In addition to this, the one-time charges for these illegal connections would have worked out to Rs 50 crore.

Further, there are long-standing defaulters who are enjoying water supply but not paying bills. The water board has a long-list of defaulters including government departments, sick industries and citizens, who have collectively accumulated arrears of nearly Rs 300 crore to be paid as bills.

There have also been complaints that people with illegal connections have been selling water at a premium to the needy.

The water board executive director, Mr Ashok Reddy, said a voluntary disclosure scheme had been offered as a one-time opportunity for consumers to regularise their illegal connections. “The scheme is valid from July 15 to September 14 and those with 15, 20 and 25 mm size connections are eligible for it,” said Mr Reddy.

Under the scheme, the water board will collect one-time connection charges and water charges for one year for the regularisation of the connection. It has warned that those failing to avail the scheme will face penalties after September 14.

Last Updated on Wednesday, 04 August 2010 05:41
 


Page 275 of 414