Urban News

  • Increase font size
  • Default font size
  • Decrease font size
Water Supply

Two major tanks in city to be linked

Print PDF

The Hindu      23.07.2010

Two major tanks in city to be linked

Special Correspondent

A culvert being built at a cost of Rs. 17 lakh; works to be completed in first week of August

– Photos: K. Ananthan

A culvert being constructed at Ukkadam to enable the flow of surplus water from the Big Tank to Valankulam and (right) garbage chokes the channel through which the surplus water has to flow to Valankulam.

COIMBATORE: A nearly seven-year campaign for a proper link to enable free flow of surplus water from the Big Tank at Ukkdam in the city to the Valankulam in the same area has yielded the desired result. A Rs.17-lakh project to build a culvert is being implemented to create the link.

The project has been taken up under the Namakku Naame Thittam. Under this, Siruthuli, a public movement to conserve water resources, has contributed 33 per cent of the project cost. The rest has been provided by the district administration from the funds of the District Rural Development Agency. The works are being carried out by the National Highways.

While de-silting tanks in the city, Siruthuli also took up the campaign for re-establishing the link between the two tanks at Ukkadam. The organisation found garbage, debris had choked a worn out pipeline and a channel that were supposed to bring the surplus from the Big Tank to Valankulam.

The blocks had led to the surplus in the Big Tank flowing back into River Noyyal. The Big Tank and Valankulam are among the eight tanks in the city that come under the Noyyal system.

The Big Tank is spread over 320 acres and has a capacity of 70 million cubic feet (mcft). The system has been designed in such a way that surplus water from this water body has to flow to the 160-acre Valankulam, the capacity of which is 27.88 mcft.

But, a study done a year ago for rejuvenation of tanks under the Jawaharlal Nehru National Urban Renewal Mission found that constructions on the Valankulam had reduced its water spread area to 96 acres and capacity to 16.7 mcft.

The effort now is to fill up the tank at least to its existing capacity. There is a culvert on the eastern side of Palakkad Road (near the Ukkadam Police Station). But, up to this point, water has to flow only through a nearly 30 ft long pipe. As this pipe is clogged and worn out, it is being replaced with a culvert that has a vent of 8 ft height and more than 16 ft breadth.

A gradient is being provided to enable smooth flow of the surplus water from the Big Tank, according to official sources. The works would be over by the end of this month or in the first week of August. Another 20 days were needed for curing. Till then, traffic would not be allowed on this stretch.

What threatens to slow down the pace of the work is a large dump of garbage and debris in the channel. The sources point out that water will not flow to Valankulam if the dump is not removed. And, once the channel is closed with slabs, the dump cannot be removed. It is not clear who will remove it – the Coimbatore Corporation or the National Highways.

Last Updated on Friday, 23 July 2010 05:20
 

Hogenakkal project to be over ahead of schedule

Print PDF

The Hindu       19.07.2010

Hogenakkal project to be over ahead of schedule

Staff Reporter

The drinking water project is being implemented in five phases

—Photo: N. Bashkaran

SPOT STUDY:Deputy Chief Minister M.K. Stalin inspecting the Hogenakkal Drinking Water Project work at Hogenakkal on Sunday.

HOGENAKKAL: The State government is committed to completing the Rs.1,928-crore Hogenakkal Drinking Water Scheme and Fluorosis Mitigation Project six months ahead of the deadline, Deputy Chief Minister M.K. Stalin said here on Sunday after reviewing the works.

Being implemented with funds from the Japan International Cooperation Agency, the project would serve a population of 30 lakh in Krishnagiri and Dharmapuri districts.

The 30-month implementation period would end in December 2012. But, with the focus on carrying out the works at a brisk pace, the project would be completed much ahead of the deadline as in the case of the Ramanathapuram Integrated Drinking Water Project, Mr. Stalin said.

The Hogenakkal project was being implemented in five phases. Under the first phase, main head works on the Cauvery river bed, the construction of a water treatment plant with a capacity to treat 1,600 lakh litres a day in Kullathirampatti village and two sumps of 1.2 lakh litres each in Madam village near Pennagaram costing Rs. 63.67 crore were in progress.

The construction of the treatment plant began on February 14 and the sumps on February 20. A more than 3,000 ft-long trench was being dug around the treatment plant to protect it from elephants.

The laying of pipelines, construction of overhead tanks and more sumps would be taken up in the next phases. So far, Rs. 57 crore had been spent on the project.

Earlier, Mr. Stalin inaugurated the construction of storage tanks at Ambedkar Colony in Dharmapuri and at Savalur in Nallampalli.

He also inaugurated the Rs.4.99-crore Pennagaram Drinking Water Supply Scheme near the Pennagaram Bus stand. The scheme would provide 70 litres per capita per day to 16,892 people. The Deputy Chief Minister also inspected the site for the proposed bus stand at Royakottai.

Last Updated on Monday, 19 July 2010 11:54
 

Late monsoon rain sees groundwater levels soar

Print PDF

Deccan Chronicle       06.07.2010

Late monsoon rain sees groundwater levels soar

July 6th, 2010

July 5: Recent studies conducted by the Chennai Metropolitan Water Supply and Sewerage Board have revealed that the groundwater level in all 10 zones of urban Chennai during the first four months of 2010, particularly sultry April, was higher than the level in the corresponding year.

The study that assesses the average water level fluctuation in the city also indicates that the level has risen steadily since this January till April before the usual fall in dry summer.

This makes it evident that Mother Nature has by far been kind to Chennaiites, be it in reducing the soaring mercury level this summer or making up for the delayed northeast monsoon late last year.

Though the rainfall was not up to the expected level in the early days of NE monsoon in 2009, heavy downpour in the fag end, particularly late November, had kept the groundwater level encouraging.

While the average water level hovered around 2.2 metres in January in the 10 zones, the same rose above 4 metres in April.

Similarly, the low evaporation level has also cheered water managers this summer, thanks to the unseasonal rain mid-June. In June alone, Tamil Nadu got 77.9 mm of rainfall as compared to a normal of 42.1 mm.

“The thundershower development is mainly because of the sea breeze, that creates instability in the atmosphere when it comes in contact with the westerly winds,” says Dr Y.E.A. Raj, deputy director of meteorology, regional meteorological centre.

 


Page 115 of 178