The Hindu 24.08.2013
Salem Mayor inspects works
Mayor S. Soundappan along with Commissioner M. Ashokan
inspected the ongoing works being carried out in Ammapet Zone at a total
cost of Rs. 9.26 crore. Construction of retaining wall is being carried
out on Ananda Bridge, after which approach road would be laid on both
the sides. The much-delayed Rs. 1.4-crore project has finally seen the
light after compensations were paid to the land owners for the acquired
land.
He also inspected construction of additional
classroom in Indira Gandhi Corporation High School in Ammapet, drainage
works in Ramanathapuram Odai, construction of overhead water tank for
the Mettur – Salem Dedicated Water Supply Scheme and other works in the
zone.